Project Update – Trumen

August 20, 2018
Project Update – Trumen

Trumen has been progressing fantastically with approximately two months remaining on site!

Corplex have already handed over:
– 25 industrial units (Buildings C and D);
– Storage King existing building (Building B zone 1);
– Cosh Living retail tenancy (Building A); and
– 26 Strata Storage units (Building A).

With the 5 hi-tech premium industrial units on level one (Building A) to be handed over shortly, the remaining works will include the additional 8 hi-tech premium industrial units (Building A), and the childcare centre and feature atrium (Building A).

The façade on Building A gives a natural feel with the integrated green walls complimenting the completed landscaping surrounding it. The landscaping for the childcare centre is now completed on the balcony play areas with the balustrade glazing and feature frames to follow.

Services are also being fit off on childcare levels 1 & 2, which will flow on to the Ground Floor. This will allow finishing trades to bring the project to a complete handover.

The site looks amazing with all hardstands complete and a large portion of the site completely handed over and operational.