Project Update – Thompson’s Gateway

January 9, 2019
Project Update – Thompson’s Gateway

Stage 1 has been completed comprising of a United Petrol Service Station, 3 food tenancies and 6 warehouse units.

Stage 2 is currently in construction and is approximately 50% completed. The external earthworks and retaining wall are now completed with external pavements following. The commercial tower’s structure is well underway with the final Post-tension slab on level 2 to be poured by the end of January with steel also beginning installation this month.

Ground floor glazing and fit out works will bring this stage to lock up in early March, with the entire project to reach completion in early June 2019.