Project Update – Nine Mine Stage 2

August 2, 2018
Project Update – Nine Mine Stage 2

The main structural works are now finished with the canopy and the façade structure nearing completion later this week. The concrete building will be linked back to nature as the timber cladding is installed over the façade to creatively portray the 9mile apple logo. The reinforcement for the office suspended slab is also being installed and, once completed, will feature an exposed concrete ceiling for the ground floor office space. The recessed dock levellers and remaining external hardstand are being prepared for their final pour and the roofing will be commencing this week as well.

We look forward to the final stages of this project as the building’s character evolves and the client’s visions come to life.