All stages of Logis Connect are progressing well and the project is really starting to take shape.
In Building A, the structure, roof plumbing and internal slabs have all been completed with the external hardstand following and the glazing installation and fitout works well underway. In Building B, the ground floor slab has been poured and the formwork for the level 1 slab is underway. In Building C, the double-storey precast concrete panels for the core have been erected and the ground floor slab is prepared to be poured. In Building D, the footings for the petrol station have been completed, the precast panels have been erected, the fuel tanks are all installed, and the in-ground services are well underway.
We are very excited to see this project coming together on site and are working hard to bring it to fruition for our clients.