Project Update – Fort Altona

May 9, 2019
Project Update – Fort Altona

Fort Altona is approaching 50% completion and is on track for handover in September.

On site, the precast panels for the 28 warehouses, the offices, and the cafe have been erected. Structural steel has also been completed for the warehouses, and has commenced for the offices and cafe. Roofing to the warehouses is well underway, while the first eight internal slabs and the northern parking lot have also been poured. We are also now benching the levels for stage 5 of the project which will include the Flexispaces.

The team have done a fantastic job bringing this development to life in such a short amount of time and we look forward to bringing the project to fruition over the coming months.