Project Update – Fort Altona

July 18, 2019
Project Update – Fort Altona

Fort Altona is well underway and on schedule for completion in September.

The precast concrete panels and structural steel is now complete with roofing to the Stage 5 Flexispaces following and progressing as scheduled. All external glazing frames have been fitted ready for glazing to be completed while roller shutter doors are being installed as we speak. Service rough-ins and plastering works are progressing in concert, with tiling and joinery works commencing shortly. The team is working hard to ensure the in-ground services to Stage 5 are completed so that concreting can continue.

Corplex are excited to see the installation of the timber-look battens, sun-shade louvres and standing-seam cladding, which will complete the external façade and showcase the architecture of this development.