Project Update – Trumen

March 16, 2018
Project Update – Trumen

The fitout to the 25 industrial units in Buildings C and D is well underway, and the driveways are being poured in stages over the next few weeks.

The three levels of the Building B fitout are also progressing well, allowing works to the new section of Building B to commence. This stage of the build is a 4 level self storage facility that Corplex are handing over as a shell including the level 2 post tension slab.

Building A has begun to take shape after months of structural work, with the level one and two post tension slabs now formed and partially poured. There is a total of 5 Post tension slab pours, with concrete beams reaching 600mm in depth!

Retail and Strata storage stages will begin fitout shortly, with the three level childcare and the 13 level-one industrial units to follow.