Project Update – Aurora

April 23, 2018
Project Update – Aurora

In-ground services are almost complete, which allows us to backfill the main service trench and commence with cladding works to the south of both buildings. Building 2 will reach lock up stage within weeks, allowing the internal fit-out to begin. Cladding works, including metal profile sheeting, high pressure laminate, fibre cement sheeting and brick tiles is well underway. Underground road boring for the new sewer will be completed shortly, with the final structural elements and concrete slabs of Building 1 to follow. The project team is working hard to manage the logistics of the tight construction space and keep the project on target.

We look forward to seeing this highly detailed project completed soon.