Project Update #6 - Trumen

08 June 2018

An occupancy permit has been received for Buildings C & D and defecting has commenced.
 
The majority of the external concrete has been poured throughout the site with the final external pours in front of Building B to follow in the coming weeks.
 
At the ground floor of building A, the shop front glazing has been installed and internal fit out for the retail has commenced, with the strata storage area close behind. Fit out & services rough in has commenced on level 1 of the childcare with ground floor & second level to commence soon. Which will be followed by the landscaping to outdoor play areas.
 
The southern Hi-Tech units’ mezzanine floors and framing has commenced, with timber staircases to follow. The final level 1 has been completed and the precast to the remaining northern hi-tech units’ will be erected next week. With steel and roofing to follow.
 
The showroom to the existing section of the Storage King facility is being finalised along with the floor finishes to the existing slab.

Gallery

Video Gallery

Trumen Update #6

News

 

Customer Testimonials

"The value in working collaboratively with Corplex as project partners meant that pricing and variation adjustments simply became a part of the conversations we had. Corplex always conducted themselves ethically therefore we had the ultimate trust in what was supplied to us at every stage".

Gary Deer – National Operations Manager Gallagher Australia
View all
 
Have any question? call us on
(03) 9922 6922
Email us

Build NEws Buzz CONNECT