Project Update #2 - Trumen

16 November 2017

Building C and D are tracking well with panels, structural steel, suspended slabs and inground services complete. Roofing and ground slabs are underway with our first pour happening next week.
 
The building B scope has grown significantly with additional works including aspects of the fitout and fire systems amongst other items. Bored piers have been completed and the precast panels/ structural steel is expected to be complete by Christmas on stage one of the build.
 
Building A footings and in ground services to the retail stage are complete with the retail slab being poured Friday 17th of November. The precast substation room is awaiting inspection and approval and precast columns will begin arriving over the next few weeks to make way for post tension level 1 slab.
 
The Corplex team have been doing an incredible job bringing this immense project to fruition, and we cannot wait to see the finalised development!

Gallery

News

 

Customer Testimonials

"The value in working collaboratively with Corplex as project partners meant that pricing and variation adjustments simply became a part of the conversations we had. Corplex always conducted themselves ethically therefore we had the ultimate trust in what was supplied to us at every stage".

Gary Deer – National Operations Manager Gallagher Australia
View all
 
Have any question? call us on
(03) 9922 6922
Email us

Build NEws Buzz CONNECT